When do I need to apply for the oversized vehicle movement (OVM) permit?


lta-logo
Updated by LTA

The OVM permit is required for vehicles exceeding width, length or weight requirements.

The width and length requirements (i.e. oversized) are as follows:

Overall width of more than 3.0 metres (or more than 2.6 metres when travelling on controlled roads); or
Rear overhang of load of 1.8 metres or 40% of the vehicle length, whichever is lesser.

The weight requirements (i.e. overweight) for the respective vehicles are as follows:

You may also use the validation check at this link.

The application must be submitted at least 3 working days before the intended date of travel. Applications submitted after noon (i.e. 12 p.m.) will be deemed as applications submitted for the next working day.